MoEFCCverified 2026-06-14amended
EIA Notification 2006
- Issued
- 2006-01-01
- Effective
- 2006-04-01
Applies to
Projects listed in the Schedule across 8 sector groups; Category A (central appraisal), B1 (state EIA + EAC), and B2 (state, no EIA).
Key points
- Sector schedule with thresholds drives Cat A vs B1 vs B2.
- Public consultation, Terms of Reference, EAC/SEIAA appraisal.
- PARIVESH 2.0 single-window since 2023; Oct 2025 OM streamlined EC↔CTE.
Applicability triggers
- Project listed in Schedule
- Capacity / area / location triggers (Cat A vs B)
Practitioner questions
- Cat A vs B1 vs B2 categorisation and what changes after the Oct 2025 OM?
- What is the typical clearance timeline post-PARIVESH 2.0 integration?
- When are public hearings exempt (B2, eco-sensitive zone exceptions)?
Sources
More in air-water
Ask the AI about EIA 2006
Three example questions — every answer cites the corpus.